COMPETITION SCHEDULE


TIMELINES OF THE GLOBAL LANDSCAPE DESIGN COMPETITION

D* = 15 Days from the date of approval from Hon’ble LG

DAYS CALL FOR ENTRIES No. of Days
D* Launch of the Global Design Competition
D+15 days Last date for clarifications 15 days
D+24 days Replies to Queries 9 days
D+58 days Closing of online registration and team building 34 days
STAGE -I
D+60 days Deadline for Stage-I submissions with self-declaration 2 days
D+64days Evaluation by the Jury and Selection of five entrants for each project site 4 days
D+67 days Announcement of Stage-I results 3 days
STAGE -II
D+69 days Uploading of Stage-II Brief for the selected entrants. 2 days
D+78 Facilitative Dialog process 9 days
D+108 days Deadline for Stage-II submissions 30 days
D+112 days Presentation before the Jury 4 days
D+120 days
(Total:4 months)
Announcement of Competition results 8 days