How to Apply

  • For Sanction/Addition/Alterations: If a person intends to erect or re-erect or make alterations in a building, he/she shall give notice in writing in the prescribed form (Form 1 Appendix 'A' Bye-Law No.6.1) and such notice shall be submitted in the proforma along with requisite documents, fee and charges mentioned therein.(Refer Annexure 'A').

  • Procedure during construction of Building : The owner/applicant who has been granted such building permit shall intimate the Authority in writing before 7 days of starting of construction work at site in the prescribed form (Form III, Appendix 'B', Bye Law No.7.2.1). He shall obtain an acknowledgement from the Authority of this notice (Refer Annexure 'B').

  • Validity Period of Building Plans:
    The building plans shall remain valid from date of sanction as mentioned below:
    • For residential, Industrial & Commercial (upto 4 stroreyed building.) - 2 years
    • For large complexes and multi stroreyed buildings and institutional buildings. - 3 years
    • No building activity can be carried out after the expiry of validity of such building permit.

    The building plans can be revalidated for a period of one year at a time form the date of expiry of validity of original permit.

  • Revalidation of Plans
    The original sanctioned plan is required to be submitted with a letter of request for revalidation along with time extension letter from the Lease Deptt. if necessary.
  • Plinth Level Permit : Ministry of Urban Development and Poverty Alleviation, Govt. of India, vide notification No.S-O1154(E) dated 21.11.2001 abolished C & D Certificates and introduced intimation of completion of work up to plinth level. Every owner/lessee, is required to submit information of completion of work upto plinth level in the prescribed form and such notice shall be submitted in the proforma along with requisite documents, fee and charges mentioned therein. (Refer Annexure 'C').

  • Completion-cum-Occupancy Certificate : No person shall occupy or allow any other person to occupy any building or part of a building for any purpose until such building or part has been granted the occupancy certificate.
    Every owner/ lessee is required to submit a notice of Completion cum Occupancy Certificate of the building in the prescribed form (Appendix B-3) Bye Law No.7.5.2. and such notices shall be submitted in the proforma along with the requisite documents, fee and charges mentioned therein.(Refer Annexure 'D').

  • Provisional Occupancy Certificate and Completion Certificate for Co-operative Group Housing Societies, Govt. Departments, Govt. Institutions, Charitable Trusts and Wakf Board: No person shall occupy or allow any other person to occupy any building or part of a building for any purpose until such building or part has been granted the provisional occupancy certificate. Every owner/ lessee is required to submit a notice of Provisional Occupancy Certificate and Completion Certificate of the building in the prescribed form (Appendix B-3) Bye Law No.7.5.2. and such notices shall be submitted in the proforma along with the requisite documents, fee and charges mentioned therein.(Refer Annexure 'E').
 
   
  Screening Committee (HOUSING & URBAN PROJECTS WING)  
   
  Master Plans  
  Zonal Plans  
  Urban Extension Projects  
  Traffic & Transportation  
  Other Projects  
  Special Projects  
  Policy Modifications  
  Building Guidelines  
  VIOLATION IN PROPERTIES